In Uttarkashi of Uttarakhand, it is the ninth day for the reason that 41 labourers have been caught within the tunnel. Efforts are ongoing to soundly rescue all of them. In the primary success for the rescue employees, a 6-inch pipe was inserted into the tunnel to evaluate the situation of the labourers. Through this pipe, necessities like food and drinks, in addition to cellphones and different objects, might be despatched to the employees. Additionally, an endoscopic digital camera might be positioned on this pipe, enabling dwell visuals of the labourers and permitting communication with them.
While 5 totally different businesses are working to make the rescue mission profitable, the administration has ready six plans to save lots of the lives of the trapped labourers. Today marks the ninth day since 41 labourers acquired caught within the tunnel collapse in Uttarkashi. To facilitate delivering necessities like meals, drinks, and even cellular chargers to the labourers, a 6-inch pipe has been inserted into the tunnel. Anshu Manish Khalho, the Director of NHIDCL, supplied additional particulars, mentioning that steady tremors have been felt in the course of the pipe insertion course of.
Uttarkashi (Uttarakhand) Tunnel Rescue | Inside visuals of the tunnel as rescue operation continues.
(Pics Source: Working Staff) pic.twitter.com/gxJRbSEA0Q
— ANI (@ANI) November 20, 2023
An escape tunnel is being constructed contained in the tunnel. Due to the motion of machines, there may be appreciable vibration within the tunnel, inflicting anxiousness among the many labourers concerned within the rescue operation. A machine for drilling from the highest of the tunnel is anticipated to reach quickly. It’s value mentioning that the DRDO (Defense Research and Development Organisation) has despatched a 20-kilogram and a 50-kilogram robotic contained in the tunnel, supposed to evaluate the scenario precisely throughout the tunnel.
टनल रेस्क्यू ऑपरेशन में बड़ी कामयाबी
मजदूरों तक पहुंचा लाइफ सपोर्ट सिस्टम
57 मीटर मलबे में आर-पार हुआ पाइप
6 इंच मोटा लाइफ सपोर्ट सिस्टम आर-पार हुआ
हर आधे घंटे में मजदूरों से कर सकते हैं बात #TunnelCollapsed #RescueOperation @shilparawat_sr pic.twitter.com/7OdbX6Bdbm
— Zee Uttar Pradesh Uttarakhand (@ZEEUPUK) November 20, 2023
NHIDCL director Anshu Manish Khalkho mentioned that the Defence Research & Development Organisation has despatched 2 robots weighing 20 kg and 50 kg respectively. “The robots move on the ground and the land is working like sand, we are apprehending whether or not would the robots be able to move there…All machinery is coming, they are mobilised and will be here within a day or two…BRO is constructing roads wherever necessary on this end and the Barkot end (to enable the movement of machinery). Roads are ready on both sides, now we are waiting for the machinery. The machines are very heavy, they cannot be airlifted,” he mentioned.